Living Report · Electrical Planning Report + EV Ready Plan
Both of Edgewater's services have more than 60% spare — and no upgrade is needed for anything assessed.
Edgewater is fed by two separate BC Hydro services, each assessed on its own. About 62 percent is unused at the service feeding Buildings 1, 2 and 3 with the amenity building, and about 69 percent at the service feeding Buildings 4 and 5. That is enough to make one stall EV Ready for every one of the 201 residential units, with capacity left over afterwards. This page carries both of your documents: the sealed Electrical Planning Report and the EV Ready Plan that turns its charging scenario into a concrete design.
516.9 kW of 831.4 kW
345.1 kW of 498.8 kW
What's inside
Explore the report, section by section.
Each tab restates the sealed reports in plain language. The PDFs remain the official record.
Executive summary · from the EPR
The Edgewater strata complex is well positioned for its current and future electrical needs. Both of the property's BC Hydro services carry enough unused capacity to make one stall EV Ready for every residential unit, with capacity left over afterwards, and no service upgrade is needed for anything assessed. There is spare for the installation of EV chargers, heat pumps and electric ranges as needed, and the gas-fired equipment can be electrified over time without an expensive service upgrade. The only scenario that would push the service over its limit is if every system were electrified all at once, including the gas boilers and pool heater.
Two points that matter for planning
- Feed charging from the main distribution, not the house distribution. At Electrical Room 1 the house distribution has less spare (216.9 kW) than the managed charging load requires, and neither house board has spare breaker positions.
- Hot water and charging draw on the same spare. A future conversion of the gas hot water systems fits, but at Electrical Room 1 the two together leave only a modest margin — so decide the order, and confirm the capacity position again before committing to the second major conversion.
Edgewater has 516.9 kW of the 831.4 kW spare at Electrical Room 1 and 345.1 kW of the 498.8 kW spare at Electrical Room 2 — enough to make one stall per unit EV Ready under managed charging on both services with capacity left over, and enough to convert the central gas hot water to electric, though at Electrical Room 1 the two together leave only a modest margin. No service upgrade is required for any load assessed.
01 · Capacity, measured
How much electrical room is left — on each service.
Capacity is assessed at the strata's own main breaker in each electrical room, using BC Hydro's hourly load data — the property's genuine busiest hour, plus the 25 percent safety factor Technical Safety BC requires. The two services do not join anywhere on the building side, so no spare transfers between them.
Spare capacity at a glance
House distribution
Each service also carries a separately metered house distribution.
Common area and building service loads only — the 400 A house switch on each service, assessed at 80 percent. These meters are reported individually, so no allocation is needed.
| Measure | Electrical Room 1 | Electrical Room 2 |
|---|---|---|
| House distribution capacity | 332.5 kW | 332.5 kW |
| House meter peak | 92.509 kWh · Jan 26, 2026 at 10:00 | 38.287 kWh · Jan 1, 2026 at 16:00 |
| House design peak demand (× 1.25) | 115.6 kW | 47.9 kW |
| House distribution spare capacity | 216.9 kW | 284.6 kW |
| House spare as a share of house capacity | 65.2 percent | 85.6 percent |
02 · Your building
Five buildings, two services, one diagram.
Edgewater is a 201-unit residential strata registered in three phases between 2013 and 2014: five three-storey wood-frame buildings over parkade, holding 48, 51, 36, 33 and 33 strata lots, plus a common amenity building with a pool, sauna, gym, kitchen, common rooms and its own elevator. Parking is in two underground parkades plus surface visitor parking — 388 stall positions in total. Tap any box in the diagram to see what it is and what it feeds.
Where the power flows
Every transformer downstream of the two main switchboards is strata-owned. Each steps 347/600 V down to 120/208 V and sits either in the electrical room or in a caged enclosure in the adjacent parkade. Everything upstream of the main breakers — the BC Hydro service conductors and the utility pad-mounted transformer — is BC Hydro's and outside the scope of the report.
Equipment schedule
What is in each electrical room.
As documented at the July 30, 2026 site visit and on the sealed one-line diagrams E500 and E530. The main switchboards, strata-owned transformers, meter centres, house panels and parkade panels are in good condition, and no condition assessment or capacity upgrade is required.
| Electrical Room 1 · Building 2 parkade · 15185 36 Avenue | ||
|---|---|---|
| Equipment | Rating | Serves |
| Main switchboard | Eaton Pow-R-Line C, 1200 A bus, 25 kA at 600 V | Whole service |
| Main breaker | 1200 A frame, 1000 A trip | First point of protection |
| Transformer TR-1 | 300 kVA on a 400 A breaker | Building 1 meter centres, 48 suites |
| Transformer TR-2 | 300 kVA on a 400 A breaker | Building 2 meter centres, 51 suites |
| Transformer TR-3 | 225 kVA on a 400 A frame, 300 A trip | Building 3 meter centres, 36 suites |
| House switch and board | 400 A at 600 V | House distribution below |
| Transformer TR-AM | 150 kVA | Amenity building, 600 A panel |
| Transformers TR-H1, TR-H2, TR-H3 | 45 kVA, 75 kVA, 45 kVA | House panels, 200 A, 225 A and 200 A |
| Standby generator | Kohler, 60 kW, 78 kVA at 347/600 V | 100 A transfer switch, 60 A emergency panel |
| Electrical Room 2 · Building 5 parkade · 15145 36 Avenue | ||
|---|---|---|
| Equipment | Rating | Serves |
| Main switchboard | Eaton Pow-R-Line C, 600 A bus | Whole service |
| Main breaker | 600 A frame | First point of protection |
| Transformer TR-5, Building 4 | 225 kVA on a 400 A frame, 300 A trip | Building 4 meter centres, 33 suites |
| Transformer TR-5, Building 5 | 225 kVA on a 400 A frame, 300 A trip | Building 5 meter centres, 33 suites |
| House switch and board | 400 A at 600 V | House distribution below |
| Transformers TR-H4, TR-H5 | 75 kVA each | House panels, 400 A each |
What draws power today
Heat is electric; hot water, ranges and the pool are gas.
The property's energy systems are split between gas and electricity. Suite space heating is electric baseboard on two 2-pole 20 A circuits per suite. Domestic hot water is gas, produced by tankless water heaters with storage tanks in each mechanical room. Suite ranges are gas, with no electrical rough-in for an electric range — which the strata council confirmed. Here is what sits on the electrical services.
03 · The future, scenario by scenario
What could go electric — and does it fit?
Pick a service, then a scenario, to see the report's estimated added load, its verdict, and what it does to the spare. The Strata Property Regulation requires the scenarios to be modelled separately rather than as one combined figure — and they all draw on the same spare. Central-system estimates follow the April 2026 CHOA guidance, converting nameplate BTU/h at a coefficient of performance of 2.5.
Electrical Room 1 · Buildings 1, 2, 3 + amenity · 516.9 kW spare
For electric vehicle charging the assessment is whether the service supports one stall per residential unit, and both services do. At Electrical Room 1, charging with the hot water conversion and the amenity boilers together would take 581.8 kW against 516.9 kW of spare. Decide the order in which to pursue them, and confirm the capacity position again before committing to the second major conversion.
The scenario tables, as printed
Electrification scenarios by service.
| Electrical Room 1 · 516.9 kW spare | ||
|---|---|---|
| Scenario | Estimated added load | Can accommodate |
| In-suite heat pumps, all suites | Approximately 0 kW net with baseboard interlock | Yes |
| Gas domestic hot water to electric | 263.6 kW | Yes |
| Amenity pool and hot water boilers to electric | 93.6 kW | Yes (with consideration) |
| Gas range to electric, all suites | 110.1 kW (6 kW per suite, apartment diversity applied) | Yes |
| EV charging, one charger per residential unit | 224.6 kW managed | Yes |
| Electrical Room 2 · 345.1 kW spare | ||
|---|---|---|
| Scenario | Estimated added load | Can accommodate |
| In-suite heat pumps, all suites | Approximately 0 kW net with baseboard interlock | Yes |
| Gas domestic hot water to electric | 128.9 kW | Yes |
| Gas range to electric, all suites | 68.7 kW (6 kW per suite, apartment diversity applied) | Yes |
| EV charging, one charger per residential unit | 109.8 kW managed | Yes |
These are planning estimates for the added equipment, not a code load calculation. The hot water figures are an upper limit, stated as such deliberately: they scale from the Building 1 plant's gas firing rate, which is the capacity to meet simultaneous draw rather than a load the building sustains. Size any replacement from a full year of the strata's gas consumption data rather than from these figures.
04 · Our recommendations
What to do, in plain order.
The report works through the electrification topics common to a strata of this type. Each is addressed even where no action is needed, so the council can see it was considered.
No service upgrade is required for any load assessed here. The next step would be for the strata council to set forth a long term plan for the highest priority items. This is a planning-level report: it gives the strata a clear, current picture of the electrical capacity and demand and satisfies the Electrical Planning Report obligation under the Strata Property Act; it is not a design. Any system-wide installation or electrification, such as converting a central gas system to electric or upgrading the main service, should be undertaken with an engineering study at that time.
Three things to do now
- Put it on file, including on your Form B. This is the legal requirement you commissioned it to meet.
- Fold the Recommendations into your planning. Use it as a starting point for strata conversations related to electrical installations or future planning.
- Share it with owners. It is written for them as much as for council.
Two questions to ask yourselves
- Does anything in the Recommendations belong in next year's budget?
- Are our owners going to want EV chargers or heat pumps installed, and have we planned for it?
You do not need to act on every future scenario now. The report shows what is possible over time so that you can plan. You act when you're ready.
When you are ready
A walkthrough with your council is included with your report — contact CF Electrical to book a session. If owners are asking about EV charging, the is where the detailed plan is laid out. When you decide to install something, CF Electrical Services provides project management services — sourcing quotes from contractors and helping you understand the options.
Part two · EV Ready Plan · BC Hydro CS-4042 · Project 2026-EPS867EVRP
Every unit's stall, EV Ready — with no service upgrade.
"EV Ready" does not mean chargers get installed. It means the infrastructure is in place so every resident can easily add a charger when they're ready — an energized, networked, managed termination at one stall per residential unit. The plan is built to BC Hydro's program standard, which is also what makes the building eligible for BC Hydro's EV rebates. Your building may choose a more limited installation; those options are on the tab.
The recommended solution
Three new EV panels, their own meters, and 51 smart circuits.
201 Level 2 networked chargers, one per residential unit, on assigned stalls in the parkades, with charging coordinated by energy management software at a 4:1 ratio across 51 branch circuits. Chargers are fed from new 400 A EV panels — each on its own 150 kVA step-down transformer from the 600 V main distribution and on a new BC Hydro meter — so EV electricity never touches the strata's common-area account, and the house distribution is untouched.
Three 400 A EV panels
51 managed circuits
The charger
Management & billing
Parkade network
Chargers arrive with the cars
Capacity after the build
The managed peak, checked against each service.
The energy management system hard-caps EV draw at one charger at full output per circuit — 226.3 kW at Electrical Room 1 and 113.2 kW at Electrical Room 2 — and those are the values used in the plan's spare capacity calculation.
| Main service spare capacity after EVSE installation | Electrical Room 1 | Electrical Room 2 |
|---|---|---|
| Main service capacity | 831.4 kW | 498.8 kW |
| Pre-EV design peak demand | 314.4 kW | 153.7 kW |
| Pre-EV spare capacity | 516.9 kW (62.2 percent) | 345.1 kW (69.2 percent) |
| Chargers · branch circuits at 4:1 | 135 · 34 | 66 · 17 |
| Managed EV peak | 226.3 kW | 113.2 kW |
| Post-EV design peak | 540.7 kW | 266.9 kW |
| Post-EV spare capacity | 290.7 kW (35.0 percent) | 231.9 kW (46.5 percent) |
How the sharing works
One breaker, four stalls — and nobody waits for a charge.
One 40 A breaker feeds a circuit shared between four parking stalls. The energy management system dynamically allocates power to whichever chargers are operating — when a car unplugs, current is instantly reallocated to the remaining cars. No matter how many cars are plugged in, the breaker is never overloaded. Tap a scenario:
06 · Resident survey insights · EV Ready Plan
97 residents answered — an unusually strong return.
The strata circulated an anonymous resident survey between July 27 and August 11, 2026, using a web link and a poster in the common areas. Respondents were not asked for their name and no response is attributed to any unit, stall or individual. The survey does not set the charging performance basis — that follows the BC Hydro program minimums — but it tells the council how residents are placed on cost, timing and demand.
Would use charging at this property
Support for adding charging infrastructure
Willingness to contribute to cost
Typical daily driving distance
Plan to get a plug-in vehicle
What the plan takes from it
Five findings, as the plan states them.
Charging demand is larger than vehicle ownership
Thirteen respondents drive a plug-in vehicle today — seven fully electric and six plug-in hybrid — but 54 would use charging here either immediately or once they have one, and a further 24 expect to have a plug-in vehicle within five years. Infrastructure sized to today's vehicles would be undersized within the period this plan covers.
Support and opposition divide on cost, not on charging
The recurring theme among those opposed is that owners who do not charge should not pay for those who do. Willingness to pay is concentrated among the people who would use the system: of the 54 who would use charging here, 24 would pay at their own stall and a further 18 say it depends on the amount, against five who would not pay. A design where users carry the running cost matches how the majority of likely users answered.
Driving distances are short
Two thirds of respondents drive 50 km a day or less and 96 percent are at or below 100 km, against the 64 km the recommended solution delivers overnight at the fully loaded managed rate and the 264 km it delivers when lightly loaded.
Every plug-in driver supports the project
Twelve of the 13 respondents who drive a plug-in vehicle support or strongly support adding charging and none is opposed, against 31 percent opposition among those who do not drive one.
A visitor-stall first step was proposed
Several respondents proposed converting a small number of visitor stalls to shared charging as a first step, ahead of a property-wide installation. That option is set out as Alternative 2 on the Cost & Alternatives tab. The recurring concerns raised — cost allocation, fire safety in an underground parkade and its effect on insurance, electrical capacity, and the low number of EVs today — were reviewed by theme; the capacity concern is answered by the assessment: both services have substantial spare and the managed system keeps the charging load inside it.
Full tabulated results · Appendix C (all 97 respondents, shares rounded)
Ownership
| Owner | 94 · 97% |
| Renter / tenant | 3 · 3% |
Parking
| Assigned or owned stall | 97 · 100% |
Vehicles in household
| 1 | 55 · 57% |
| 2 | 39 · 40% |
| 3+ | 3 · 3% |
Currently drive an EV or plug-in hybrid
| Yes, fully electric | 7 · 7% |
| Yes, plug-in hybrid | 6 · 6% |
| No | 84 · 87% |
Would use charging at this property
| Yes, right away | 16 · 16% |
| Yes, once I have a plug-in vehicle | 38 · 39% |
| Not sure | 10 · 10% |
| No | 33 · 34% |
Support for adding charging infrastructure
| Strongly support | 25 · 26% |
| Support | 12 · 12% |
| Neutral | 18 · 19% |
| Have questions or concerns | 16 · 16% |
| Opposed | 26 · 27% |
Where they charge or would charge
| At this building, already have charging | 7 · 7% |
| Would rely on charging at this building | 12 · 12% |
| Public charging stations | 4 · 4% |
| Not applicable | 70 · 72% |
| No answer | 4 · 4% |
Willingness to contribute to cost: willing to pay at my stall 28 (29%) · depends on the amount 24 (25%) · prefer a shared option 5 (5%) · not sure 11 (11%) · not willing to pay 27 (28%) · no answer 2 (2%). The stall or unit reference, free-text comments and submission time are not reproduced anywhere, so no response can be traced to a household. The same results are filed with the plan as Edgewater_EPS867_Survey_Results.xlsx.
07 · Cost, rebates & alternatives · EV Ready Plan
What it costs, and what BC Hydro pays back.
The infrastructure is the strata's one-time build: the managed 4:1 installation and the parkade network. Chargers are a separate, owner-selected cost per stall, added as owners acquire electric vehicles. Pricing is before tax and valid for 30 days from the plan date of August 24, 2026; final pricing is confirmed by the installing contractor at detailed design.
Alternatives considered
Two other designs were on the table.
The recommended 4:1 managed solution delivers full BC Hydro charging performance at the lowest installed cost per stall while keeping ample spare at both services, separates EV consumption onto its own meters so residents without EVs carry none of the running cost, secures the $120,000 infrastructure rebate, and gives a clear path for owner enrolment as EVs are purchased. Here is what else was considered, and why.
Alternative 2 · Shared charging at visitor stalls, as a first phase
Eight shared Level 2 chargers on two managed branch circuits at visitor stalls, pay-per-use and open to any resident, deferring the property-wide installation — a connected load of 53.2 kW. Electrical Room 2 is the better location: the Building 4 electrical room has floor space, existing telecommunications service and visitor stalls immediately outside it, and Buildings 4 and 5 hold 18 of the property's 27 underground visitor stalls. Fed from a new EV panel on the main distribution, because the house distribution has no spare breaker positions.
Rebates: the infrastructure rebate is tied to one stall per residential unit, so a visitor-stall phase does not qualify; the standalone charger rebate (50 percent, to $2,000 per charger and $14,000 per complex) does apply, returning about $8,000 on eight chargers. Converting visitor stalls needs confirmation against the City of Surrey development permit parking schedule, and the six accessible visitor stalls are not candidates. The survey supports this step: 54 respondents would use charging here, five expressly prefer a shared option, and several proposed exactly this sequence.
Alternative 1 · One DC fast charger at a shared stall
A single Teal 30 kW dual-gun DC fast charger (model I-RF-4G-D-CCS-NACS) at a visitor or common stall, pay-per-use. One CCS1 and one NACS connector, 100 A at 150 to 1000 V dc, adding roughly 150 to 200 km of range per hour to a mid-size vehicle. Estimated cost approximately $40,000 before tax — the charger at $19,550 together with the step-down transformer, feeder, concrete and mounting work and installation labour — plus a Foresta network fee of $360 per year. It requires a three-phase supply between 340 V and 528 V, so it connects to neither the 600 V distribution nor the 120/208 V secondary directly and needs a dedicated transformer.
Why not selected: one unit serves one or two vehicles at a time rather than making one stall per residential unit EV Ready. It therefore does not meet the BC Hydro EV Ready requirement and does not qualify for the $120,000 infrastructure rebate, and fast charging suits short stops rather than the overnight charging pattern the resident survey describes.
This is a planning-level document for strata budgeting, BC Hydro EV Ready program submission, and reference by the strata's project design professional during detailed design — not a permit package or final design. The strata is responsible for obtaining council approval, notifying BC Hydro before energizing any additional load under the BC Hydro Electric Tariff, and obtaining all required electrical permits. Detailed design, permit drawings and construction drawings are prepared under a separate arrangement.
08 · Methodology & the fine print
For those who want to check the math.
How the capacity was measured, what standards the reports follow, what they are not, and the questions owners ask most.
Calculation worksheet · Appendix C of the EPR
Capacity, demand and spare, line by line.
| Line | Electrical Room 1 | Electrical Room 2 |
|---|---|---|
| Main overcurrent device | 1000 A trip at 347/600 V | 600 A at 347/600 V |
| Capacity, amps × volts × 1.732 × 0.80 | 831.36 kW, stated as 831.4 kW | 498.82 kW, stated as 498.8 kW |
| House switch capacity, 400 A × 600 V × 1.732 × 0.80 | 332.5 kW | 332.5 kW |
| Aggregated account peak, all 202 metered points | 374.509 kWh | 374.509 kWh |
| Suites served, of 201 | 135 | 66 |
| Allocated peak, account peak × suites ÷ 201 | 251.535 kWh | 122.974 kWh |
| Design peak demand, allocated peak × 1.25 | 314.42 kW, stated as 314.4 kW | 153.72 kW, stated as 153.7 kW |
| Spare capacity, capacity less design peak | 516.94 kW, stated as 516.9 kW | 345.10 kW, stated as 345.1 kW |
| Spare as a share of capacity | 62.2 percent | 69.2 percent |
| EV: connected load, chargers × 6.656 kW | 898.6 kW | 439.3 kW |
| EV: managed peak, connected load ÷ 4 | 224.6 kW | 109.8 kW |
| EV: spare after installation · share of capacity | 292.3 kW · 35.2 percent | 235.3 kW · 47.2 percent |
| Gas range to electric: 6 kW × apartment diversity factor sum (18.35 / 11.45) | 110.1 kW | 68.7 kW |
| Hot water: gas input scaled at 16,658 BTU/h per suite ÷ 3,412 ÷ COP 2.5 | 263.6 kW | 128.9 kW |
| Amenity pool and hot water boilers, 798,000 BTU/h ÷ 3,412 ÷ 2.5 | 93.6 kW | Not applicable |
| In-suite heat pumps with baseboard interlock | Approximately 0 kW | Approximately 0 kW |
The EV Ready Plan sizes the managed peak by circuit count instead — 34 circuits at Room 1 and 17 at Room 2, each at one charger's full 6.656 kW output — giving 226.3 kW and 113.2 kW, and post-EV spare of 290.7 kW (35.0 percent) and 231.9 kW (46.5 percent). Both documents reach the same conclusion: full EV Ready coverage fits within both services with useful capacity behind it.